A and B together can complete a work in 3 days. They started together but after 2 days, B left the work. If the work is completed after 2 more days, B alone could do the work in how many days?
[SSC 2007]
90 men are engaged to do a piece of work in 40 days, but it was found that in 25 days, two-third of the work is completed. How many men should be allowed to go off so that the work may be finshed on time?
[SSC 2008]
36 work men are employed to finish a certain work in 48 days. But it is found that in 24 days only work is done. How many more men must be taken to finish the work in time.
[LIC ADO 2007]
If 12 men or 18 women can do a piece of work in 14 days. How long will 8 men and 16 women take to finish the work?
[Railways 2007]
20 men complete one-third of a project in 20 days. How many more men should be employed to finish the rest of project in 25 more days?
[GBO 2007]
--Share with your friends --