Time and Work-Basic test 2

21)

X can do 14 of a work in 10 days, Y can do 40% of the same work in 40 days and Z can do 13 of the work in 13 days. Who will complete the work first?


Discussion
22)

A and B can complete the work in 8 days working together. B alone can do it in 12 days. After working for 4 days, B left the work. How many days will A take to complete the remaining work?


Discussion
23)

A can do a piece of work in 10 days while B can do it in 6 days. B worked at it for 4 days. How long will A take to finish the remaining work? 


Discussion
24)

P can do a piece of work in 12 days while Q alone can finish it in 8 days. With the help of R, they can finish the work in 4 days. How long will R take to finish the work at alone?


Discussion
25)

A takes twice the time taken by B and thrice the time taken by C to do a particular piece of work. Working together, they can complete the work in 2 days. Find the number of days taken by A, B and C respectively to complete the work alone?


Discussion