A is thrice as good a workman as B and therefore is able to finish a job in 30 days less than B. How many days will they take to finishthe job working together?
[Railways 2007]
Explanation
Let A take a and B take 3a days to finish the work.
As per the question,
3a-a=30
Time taken by B to complete the work is 3a
So 3×15=45 days
Therefore 1 day work of (A+B)=
Hence, (A+B) will finish the work in
Hence option C is correct