Rita can complete a job in 40 days. In how many days will she complete 3 such jobs?


  • Explanation

    We know that Time and Work are directly proportional to each other. In other words More work requires more Time.

    Here, Rita completes a job in 40 days.

    So, 3 similar jobs require 40×3=120 days

    Hence option C is correct

     