12 men can do a piece of work in 24 days, how many days are needed to complete the work if only 8 men do this work?
[IDBI officers 2010]
Explanation
According to the formula,
M1D1W2=M2D2W1
M1=12, D1=24, M2=8, D2=?
Hence option B is correct