90 men are engaged to do a piece of work in 40 days, but it was found that in 25 days, two-third of the work is completed. How many men should be allowed to go off so that the work may be finshed on time?
[SSC 2008]
Explanation
Here,
M1 = 90, D1 =25, W2 =
M2 = 90-x, D2 = 15, W1 =
So according to the formula,
M1 D1 W2 = M2 D2 W1
Hence option B is correct