Q)

90 men are engaged to do a piece of work in 40 days, but it was found that in 25 days, two-third of the work is completed. How many men should be allowed to go off so that the work may be finshed on time?

[SSC 2008]


  • Explanation

    Here,

    M1 = 90, D1 =25, W2 =1-23

    M2 = 90-x, D2 = 15, W1 = 23

    So according to the formula,

         M1 D1 W2 = M2 D2 W1

    90×25 1-23=90-x ×15×2390×25×13=1090-x75=90-Xx=90-75=15 men

    Hence option B is correct