36 work men are employed to finish a certain work in 48 days. But it is found that in 24 days only work is done. How many more men must be taken to finish the work in time.
[LIC ADO 2007]
Explanation
Here,
M1 = 36, D1 =24, W2 =
M2 = 36+x, D2 = 24, W1 =
So according to the formula,
M1 D1 W2 = M2 D2 W1
Hence option A is correct