If 12 men or 18 women can do a piece of work in 14 days. How long will 8 men and 16 women take to finish the work?

[Railways 2007]


  • Explanation

    As per the question,

    12 men = 18 women

    So 1 man = 1812 women

    ⇒ 8 men = 1812×8=12 women

    Here,

    M1 = 18, D1 =14, W2 =1

    M2 = 12+16, D2 = ?, W1 = 1

    So according to the formula,

         M1 D1 W2 = M2 D2 W1

       18×14×1=12+16×D2×1        D2=18×1428=9 days

    Hence option A is correct