20 men complete one-third of a project in 20 days. How many more men should be employed to finish the rest of project in 25 more days?
[GBO 2007]
Explanation
Here,
M1 = 20, D1 =20, W2 =
M2 = 20+x, D2 = 25, W1 =
So according to the formula,
M1 D1 W2 = M2 D2 W1
Hence option C is correct