3 men can do a piece of work in 6 days. 5 Women can do the same work in 18 days. If 4 men and 10 women work together, then how long will it take to finish the work?
[Bank PO 2010]
Explanation
According to the question,
3 men can do a piece of work in 6 days. 5 Women can do the same work in 18 days
So, 3 × 6 = 5 × 15
⇒18 men = 90 women
⇒1 man = 5 women
Here,
M1= 5, D1=18, W2=1
M2= 30-x, D2= ?, W1= 1
So as per the formula,
M1 D1 W2 = M2 D2 W1
Hence option A is correct.