3 men can do a piece of work in 18 days. 6 children can also do that work in 18 days. If 4 men and 4 children together will finish the work in how many days?
[Bank Clerks 2010]
Explanation
According to the question,
3 men can do a piece of work in 18 days. 6 children can also do that work in 18 days.
So, 3 men =6 children
⇒ 1 man = 2 children
∴ 4 men + 4 children (2 men)
⇒ 4 men + 2 men = 6 men
Here,
M1 = 3, D1 =18, W2 =1
M2 = 6, D2 = ?, W1 = 1
So according to the formula,
M1 D1 W2 = M2 D2 W1
Hence option D is correct.