A alone can complete a work in 6 days & B alone can complete the same work in 12 days. In how many days can A & B together complete the same work?

[Bank Clerks 2009]


  • Explanation

    According to the question,

    In 1 day,

    work completed by A= 16

    work completed by B= 112

    Work completed by= 16+112=2+112=312=14

    ∴ (A+B) will complete the work in 4 days.

    Hence option C is the correct 