A is thrice as good a workman as B and therefore is able to finsih a job in 30 days less than B. How many days will they take to finish the job working together ?
[Railways 2011]
Explanation
According tot he question,
A takes x and B takes 3x days to finish the job
⇒ 3x - x=30
∴ x==15 days
Time taken by B to complete the work = 3x = 3×15= 45 days
In 1 day (A+B) can complete
∴ (A+B) will finish the work in days
Hence option C is the correct.