8 men can do a piece of work in 10 days. How many men are needed to complete the work in 40 days?


  • Explanation

    Here,

    M1 = 8, D1 =10, W2 =1

    M2 = ?, D2 = 40, W1 = 1

    So according to the formula,

         M1 D1 W2 = M2 D2 W1

    8×10×1=M2×40×1M2=8×1040=2 men

    Hence option B is the correct.