X can do of a work in 10 days, Y can do 40% of the same work in 40 days and Z can do of the work in 13 days. Who will complete the work first?
Explanation
According to the question,
Time taken to complete the work by
X= 10×4= 40 days
Y= days
Z= 13×3= 39 days
∴ Z will complete the work first.
Hence, option C is the correct.