A and B can complete the work in 8 days working together. B alone can do it in 12 days. After working for 4 days, B left the work. How many days will A take to complete the remaining work?
Explanation
According to the question,
In 1 day,
(A+B) together can complete th of the work
B can complete th of the work
∴ A can complete the work
So, A can complete the work in 24 days.
Now, B's 4 day's work
Remaining work
As, time taken by A to complete the work= 24 days
∴ Time taken by A to do of the work days
Hence option A is the correct.