Q)

A can do a piece of work in 10 days while B can do it in 6 days. B worked at it for 4 days. How long will A take to finish the remaining work? 


  • Explanation

    According to the question,

    while B can do it in 6 days, B worked at it only for 4 days,

    so, the work completed by B in 4 days=16×4=23

    Remaining work=1-23=13

    A can do this work in 10 days,

    So, in 1 day A can complete110th of the work

    ∴ 13rd of the work is finished by A in 10×13=313 days

    Hence option A is the correct.