P can do a piece of work in 12 days while Q alone can finish it in 8 days. With the help of R, they can finish the work in 4 days. How long will R take to finish the work at alone?


  • Explanation

    According to the question,

     

    In 1 day,

    P can complete 1 12th of the work

    Q can complete 18th of the work

     (P+Q) together can complete =112+18=2+324=524th of the work

     ∴ (P+Q+R) will complete 14th of the work

     

       R can complete (P+Q+R)-(P+Q)

    =14-524=6-524=124

     ∴ R will finish the work alone in 24 days.

     Hence option E is the correct.