'A' can do piece of work in 60 days while 'B' alone can do it in 90 days. They begin together but 15 days before the completion of the work, 'B' leaves off. Find the total number of days for the work to be completed.
Explanation
Here, a=60, b=90, x=15
As per the formula,
Hence option A is the correct.