When 'A' alone does a piece of work, he takes 25 days more than the time taken by (A+B) to complete that particular work while 'B' alone takes 49 days more than the time taken by (A+B) to finish the same work. A and B together will take what time to finish this work?
Explanation
Here we can use the formula,
here a=25, b=49
Hence option A is the correct.