'A' takes twice as much as 'B' and thrice as much as 'C' to complete a piece of work. They together complete the work in 1 day. In what time will 'A' alone complete the work?
Explanation
Time taken to complete the work by
C=x days
A=3x days
According to the question,
Time taken to by Ais 3x
So, 3×2=6 days
Hence option C is the correct.