30 men can do a piece of work in 16 days. How many men would be required to do the same work in 20 days?


  • Explanation

    According to the formula,

    M1 D1 = M2 D2

    M1 = 30, D1 =16, M2 = ?, D2 = 20,

    M2=30×1620=24 men

    Hence option D is the correct.

    For more Short tricks and formulae click 